Oracle says OpenAI contract fully funded after $20 billion capital raise
Oracle confirmed its $300 billion OpenAI infrastructure deal is covered by a November $20 billion raise and outlined new data‑center projects in Texas.
Key takeaways
- Oracle completed a $20 billion financing round in November, half equity and half debt.
- The company says its OpenAI infrastructure build is completely funded and does not depend on further vendor deals.
- Oracle plans to add 4.5 GW of U.S. data‑center capacity, including a new campus in Shackelford County, Texas.
Oracle told investors on Friday that the infrastructure work it is doing for OpenAI is fully financed and will not require any additional vendor commitments.
Financing details and investor‑day guidance
The company disclosed that a $20 billion capital raise closed in early November, with roughly $10 billion raised through a stock offering and another $10 billion obtained via debt instruments.
At its Las Vegas investor day in October, Oracle set a ceiling of $20 billion for new capital‑market funding through fiscal 2030 and imposed a net‑debt limit of 3.5 times adjusted EBITDA.
Oracle added that ongoing private talks with other suppliers are merely “additional options” and do not affect its ability to meet the OpenAI commitment.
The firm reported a negative free‑cash‑flow figure of $23.7 billion for fiscal 2026, noting that it had previously relied on vendor financing, customer‑supplied hardware and pre‑payments to fund its build‑out.
Scale of the OpenAI partnership and related backlog
The OpenAI agreement, valued at about $300 billion over five years, represents Oracle’s largest single contract and sits within a broader backlog of $664 billion.
Customers have prepaid $11.36 billion of first‑quarter capital spending, while total borrowings stood at $125.34 billion as of August 31, according to the company’s latest filing.
Microsoft’s decision this month to wind down a 2023 AI‑computing rental arrangement with Oracle added uncertainty, but Oracle said demand for its AI services, including older GPU models, remains robust.
Data‑center expansion in Texas
Oracle and OpenAI plan to install an additional 4.5 gigawatts of capacity across the United States, building on the first “Stargate” site in Texas.
The Abilene campus, where the Astra‑6 model was trained, is nearing completion, and a second gigawatt‑scale facility will be located in Shackelford County, Texas, where all permits have already been secured.
Nvidia’s next‑generation Vera Rubin racks are slated for delivery to Oracle’s data halls in the coming weeks, completing the hardware stack for the new sites.
Share price movement and financial outlook
Oracle’s stock closed at $101.19 on Friday, down 8.5 percent, but rose 1.7 percent in after‑hours trading after the financing announcement.
The company reiterated its cash‑generation targets, expecting positive free cash flow in the second half of fiscal 2028 and more than $30 billion in cash flow for fiscal 2029, when it intends to fund growth internally.
Oracle described itself as the first hyperscaler to be fully funded for this investment cycle, a claim it said counters any media reports suggesting otherwise.